Sunday 6 September 2015

Exteral walls and more landscape photos

The house was finally "locked up" in July 2015.



External tiles were added to the rear walls of house shortly after this photo was taken ( pics in next blog) 






Photo shows concrete retaining walls , gabian retaining walls and east elevation of house. 





This is the view from the rear of house looking east. 

External cladding

Wall frames are completed with windows fitted. Roof sheeting is also fitted. Next job is the external Travetine tiles.



External wall tiles to bedroom wall. Tiles are imported from china by WestChina Trading.


Finished wall tiles.


Tiles being fitted to front wall over two layers of firbe cement sheeting.




Finished front wall.

timber wall frames


next job after the concrete was poured in March was the timber wall frames and aluminum windows. The windows have been in storage for a few months, so was good to start fitting them .



the windows are double glazed to help with our 6.5 star energy rating and were imported form china by WestChina Trading.


90 x 35 treated pine was used for the timber wall frames.




Note the electrical cables coming up through concrete slab. These are the main power supply, telephone line and data line ( to monitor the solar power system) 






Looks like timber frames are everywhere. In fact there is not a huge number of walls. We managed to make and fit all the frames in a few days. 


Photo shows front door and windows are fitted. Builders construction paper is also fitted to help with insulation. 


                      

Corner window to bedroom, both doors slide with no corner posts.




Same window showing view to the outside.



Roof sheeting being fitted, using concealed fixing clips so that there are now fixing screws through the roof sheeting to minimise the chance of the roof leaking.















Concrete slab and walls


.the structural steel was completed in october and many months were spent getting the steel formwork done to take the concrete slab



Steel roof sheeting was used as formwork for the concrete deck.






Steel formwork is in place along with the top steel ring beam. Z200 steel purlins have been bolted in place. Just needs steel mesh for the concrete and the plumbing pipes fitted prior to concrete.


A great team pouring the concrete slab.


Concrete is finished , the verandah areas down each side and the alfesco area ( closest to photograper) will be honed finish using concrete polishing machine.




Honed finish on concrete took three days to complete. ( most of the time was spent on cleaning up the mess).