Now that the house is at lockup stage , we started fitting the gyprock sheeting to the ceilings and walls
Our Retirement House
An owner-builder project
Saturday, 26 March 2016
Sunday, 6 September 2015
External cladding
Wall frames are completed with windows fitted. Roof sheeting is also fitted. Next job is the external Travetine tiles.
timber wall frames
the windows are double glazed to help with our 6.5 star energy rating and were imported form china by WestChina Trading.
Note the electrical cables coming up through concrete slab. These are the main power supply, telephone line and data line ( to monitor the solar power system)
Looks like timber frames are everywhere. In fact there is not a huge number of walls. We managed to make and fit all the frames in a few days.
Photo shows front door and windows are fitted. Builders construction paper is also fitted to help with insulation.
Corner window to bedroom, both doors slide with no corner posts.
Same window showing view to the outside.
Concrete slab and walls
Steel roof sheeting was used as formwork for the concrete deck.
Steel formwork is in place along with the top steel ring beam. Z200 steel purlins have been bolted in place. Just needs steel mesh for the concrete and the plumbing pipes fitted prior to concrete.
A great team pouring the concrete slab.
Concrete is finished , the verandah areas down each side and the alfesco area ( closest to photograper) will be honed finish using concrete polishing machine.
Honed finish on concrete took three days to complete. ( most of the time was spent on cleaning up the mess).
Wednesday, 2 July 2014
Structural steel continues
The slow process of completing the structural steel sub floor continues. Now being June we are losing some production with wet days. Photos show the completed sub floor steel with the much larger ( PFC230) welded to the outer perimeter of the building. Steel columns are also welded in place, twin posts at the front and single at the rear edge. Another channel will be fitted on top of these posts. Getting up there will be a challenge at 4 metres above ground and weighing about 140 kgs.
www.westchina.biz
Part of the steel formwork in place for the concrete floor.
In between welding the steel frame, the concrete leech drains are put in place. Note the drainage stone being used is from recycled concrete, a very inexpensive product.
A DIY 12volt electric winch being used to lift the top beams into place were they are then welded to the columns. The winch is from a quad bike and worked a treat! One beam is inplace and another ready for lifting. Note the treated pine timber fixed to the top of the beam is to fit the gutter to, much easier than trying to fix to 10 mm thick steel .
Once the beams are fitted the z200 purlins will be bolted to the ring beam .
Arriving in two weeks are all the aluminium windows and doors from China, purchased through WestChina Trading
Thursday, 8 May 2014
Gardens
While i' m busy welding the steel structure christine has been establishing our new garden . With the recent rains the plants should be well established over winter and will look great when we move in.
Subscribe to:
Posts (Atom)